Performance Optimization of a Petrochemical Cooling Tower via Fill Replacement: Cleanflow vs Cleanflow Plus

Advance Sustainable Science, Engineering and Technology (ASSET)
Universitas Persatuan Guru Republik Indonesia Semarang

📄 Abstract

This study investigates the performance improvement of an induced draft, counterflow cooling tower after replacing the existing Cleanflow fill with Cleanflow Plus. One cell (E) was upgraded while four cells (A–D) served as the baseline under CTI ATC-105 procedures. Measurements included outlet temperature, wet-bulb temperature, circulation flow, and fan power. Results show that Cell E achieved a higher cooling range (9.20°C vs. 8.63°C average) and a lower approach (6.29°C vs. 6.87°C average). Heat-transfer capacity increased from 37.12 MW average to 39.60 MW (+6.68%). Tower capability improved from 89.00% average to 94.47% (+5.47% absolute, +6.1% relative). Number of Transfer Units (NTU) increased significantly from 2.341 to 2.889 units (+23.4%), and effectiveness improved from 71.5% to 75.9% (+6.1%). Evaporation increased from 1.21% to 1.29% (6.6%), while electrical fan power was 149.65 kW (+2.4% relative to baseline). These enhancements are attributed to the higher specific surface area (140.7 m²/m³ vs. 127.0 m²/m³, +10.8%) and improved wettability of Cleanflow Plus fill. The findings support phased implementation and further optimization across remaining cells.

🔖 Keywords

#Cooling tower; fill media; heat transfer; thermal performance; optimization

ℹ️ Informasi Publikasi

Tanggal Publikasi
31 May 2026
Volume / Nomor / Tahun
Tahun 2026

📝 HOW TO CITE

Putra Hidayat, Demas Ahmad Resha; Berkah Fajar Tamtomo Kiono; Sri Widodo Agung Suedy, "Performance Optimization of a Petrochemical Cooling Tower via Fill Replacement: Cleanflow vs Cleanflow Plus," Advance Sustainable Science, Engineering and Technology (ASSET), May. 2026.

ACM
ACS
APA
ABNT
Chicago
Harvard
IEEE
MLA
Turabian
Vancouver
DOI

🔗 Artikel Terkait dari Jurnal yang Sama

📊 Statistik Sitasi Jurnal